Comment
Tuesday, November 6, 2001
Why
donors walked out on Kisumu
By
SHAKEEL SHABBIR AHMED
Two
recent Nation commentaries on Kisumu's
dire water treatment crisis and the council's alleged inaction had a hint of
mischief by some negative-minded interested parties.
I
wish to make the following comments to correct this:
Effluent
Pollution: It is true that the Kisat sewerage waste water treatment plant has
not been working for nearly 10 years and as a result industrial effluent flows
into the lake untreated. The Lake Victoria Environment Management Project (LVEMP)/World
Bank project, which we initiated in September 2000, is to concentrate on
treatment of waste water effluent and sewerage. The project was initially for an
amount of Sh150 million. We followed the procedure and satisfied all the
requirements and, as a result, LVEMP advertised the planned required works. The
tender was a local tender and a number of local contractors applied. In
February/March the tender was evaluated.
Meanwhile,
a consultant was engaged and the intervention project was re-assessed and it was
estimated that the revised increased work programme would cost Sh287 million. In
April 2001, the World Bank approved the increased value of Sh287 million. We
were delighted by this news but our delight was very short lived. The World Bank
representative then informed us that since the value of the works was in excess
of Sh250 million, it must be re-advertised internationally. Furthermore, the
process would take a minimum of 24 months before any work could start.
World
Bank moved the goal posts
We
were devastated since all along we were told that the project would start by
May/June 2001.
We
also felt that the World Bank moved the goal posts at the last minute without
reference to us as the beneficiaries.
We
even suggested that the first phase valued at Sh150 million should start and the
increased value of Sh137 million can be tendered internationally.
We
argued and pleaded that the Kisat treatment was an emergency and that this
should be rehabilitated immediately at the estimated cost of Sh20 million –
being less than 10 per cent of the value of the revised project.
The
World Bank official was unmoved, however, and told us that we had no option
since they required a holistic approach even if it meant that raw untreated
effluent would be discharged in the lake in the meantime.
We
do we understand the logic, especially since the environmental consequences of
the delay are disastrous and will not be able to be reversed. We even appealed
in June to the then World Bank country representative, Mr Harold Wackman, to
intervene and urge the World Bank to release Sh20 million for the renovation of
the Kisat treatment works as a priority bases. We have yet to hear from him.
As
such, the assertion that Kisumu Municipal Council officials should have known
about the Bank's conditions earlier is incorrect. This additional condition was
sprung on to us at the last minute in April 2001 and without any warning.
The
Jica project proposal: This proposal came in 1996 and in 1997 a feasibility study was
conducted at a cost of nearly Sh200 million to identify the extent of the
intervention required to rehabilitate and extend the provision of water and
sewerage infrastructure to meet the needs of the residents of Kisumu.
The
conditionalities of the Jica proposals were as follows:
(a)
Commercialisation of the water department
(b)
Proposal for capacity building
(c)
Institutional building proposal
(d)
provision of land for the additional development
(e)
Kisumu municipality to provide 15 per cent of the project cost of Sh6 billion,
that is Sh900 million
(f)
Guarantee of the Government of Kenya
The
Municipality of Kisumu met conditions (a) to (d) and required the Central
Government to meet conditions (e) and (f).
The
Jica proposal was forwarded to the Treasury over three years ago and
mysteriously disappeared, only to miraculously reappear after the issue was
raised in Parliament in June 2001. We were then informed that the proposal was
forwarded to the Ministry of Local Government as required.
The
Permanent Secretary and the Minister of Finance have since advised us that the
Government cannot guarantee any loan due to IMF restrictions.
Yet
the Nation editorial writer said the
Jica proposal was withdrawn due to the fact that the Kisumu Municipal Council
had "dithered and prevaricated for months". Again, this is not true.
Much of the blame lies at the doorstep of the Treasury for not acting for nearly
four years.
Three
directors representing stakeholders
Kisumu
is committed to improving its services, its residents and privatising the
provision of water, so that it is more efficient and serves the needs of
residents. We have already formed a private limited company and are in the
process of implementing the transition to operational change.
In
an effort to ensure transparency and stakeholder participation the water company
will have three directors representing stakeholders. We have even advertised
invitations to committed residents of integrity and experience to apply for
these three posts.
What
else can we do to prove that we are serious about changing things for the
better?
·
Shakeel
Shabbir Ahmed, a nominated councillor, is the Mayor of Kisumu, which will be
celebrating its centenary in December.